If 'A' is the optimistic time, 'B' is the pessimistic time and 'C' is the most likely time of an activity, then the expected time of activity is:
  • CUET (PG) - 2025
  • CUET (PG)
  • Mechanical Engineering
  • Project Management
Arrange the following elements of a feedback control loop in the correct order: (A) Actuator (B) Error detection (C) Controller (D) Feedback sensor Choose the correct answer from the options given below:
  • CUET (PG) - 2025
  • CUET (PG)
  • Mechanical Engineering
  • Project Management
Which one of the following is the excess of variable time over the activity time when all jobs start as early as possible?
  • AP PGECET - 2024
  • AP PGECET
  • Mechanical Engineering
  • Project Management

Consider the network diagram shown in Figure. The time estimates in days along the arrows represents the activities. The project completion time in days based on critical path is

  • AP PGECET - 2024
  • AP PGECET
  • Mechanical Engineering
  • Project Management

Activities A, B, C, and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other. 

The probability that the project will be completed within 40 days is _________ (round off to two decimal places).

  • GATE ME - 2021
  • GATE ME
  • Mechanical Engineering
  • Project Management