Question:

Match List-I with List-II.

List-IList-II
A. Dummy activity
B. Critical path
C. PERT activity
D. Critical Path Method
I. Follow B distribution
II. Built on activity oriented diagram
III. Constructed only to establish sequence
IV. Has zero total slack

Show Hint

Critical path → zero slack; Dummy → only sequencing.
Updated On: May 22, 2026
  • A-IV, B-II, C-III, D-I
  • A-III, B-IV, C-I, D-II
  • A-IV, B-I, C-II, D-III
  • A-III, B-IV, C-II, D-I
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Concept: PERT/CPM terminology:

Step 1: Dummy activity (A).


• Has zero duration
• Used only to maintain precedence relationship Thus: \[ A \rightarrow III \]

Step 2: Critical path (B).


• Longest path in network
• Has zero slack Thus: \[ B \rightarrow IV \]

Step 3: PERT activity (C).


• Probabilistic time estimation
• Follows Beta distribution Thus: \[ C \rightarrow I \]

Step 4: Critical Path Method (D).


• Deterministic
• Activity-oriented network Thus: \[ D \rightarrow II \]

Step 5: Final matching.

\[ A-III,\; B-IV,\; C-I,\; D-II \] \[ \boxed{\text{Answer: Option (2)}} \]