A project network with the sequence of five activities is shown.
A project network with the sequence of five activities
The crashing costs of activities are
ActivityABCDE
Duration (week) 56834
Crashing cost per week (lakh INR)4.02.52.03.04.0
If the project is crashed by one week, the increase in project cost, in lakh INR, is
  • GATE MN - 2024
  • GATE MN
  • Systems Engineering
  • Network Analysis

A project network consists of the following activities

\[\begin{array}{|c|c|c|} \hline \textbf{Activity} & \textbf{Immediate Predecessors} & \textbf{Duration (days)} \\ \hline \text{A} & \text{--} & 3 \\ \hline \text{B} & \text{--} & 4 \\ \hline \text{C} & \text{A, B} & 5 \\ \hline \text{D} & \text{B} & 6 \\ \hline \text{E} & \text{D} & 7 \\ \hline \text{F} & \text{C, E} & 8 \\ \hline \text{G} & \text{D} & 9 \\ \hline \text{H} & \text{F, G} & X \\ \hline \end{array}\]
 

If the project completion time is 30 days, then the value of \( X \), in days, is \(\underline{\hspace{2cm}}\) (in integer).