Question:

The three phases involved in the management of large projects are:

Show Hint

Think of the "PSC" mnemonic: Plan it, Schedule it, Control it. If you aren't controlling the project after it starts, the planning and scheduling were useless!
Updated On: May 20, 2026
  • Planning, scheduling, evaluating
  • Planning, scheduling, controlling
  • Scheduling, designing, operating
  • Scheduling, operating, evaluating
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Concept: Project management is a structured process used to achieve specific project goals. For large-scale engineering projects, this is traditionally divided into three core functional phases.

Step 1:
Breakdown of the three phases.

Planning: This involves setting goals, defining the project, and identifying the required resources, tasks, and team organization.
Scheduling: This involves the creation of a detailed timeline. It assigns people, money, and supplies to specific activities and relates activities to each other (e.g., using CPM or PERT).
Controlling: This is the ongoing process of monitoring resources, costs, quality, and budgets. It involves comparing actual progress against the schedule and taking corrective action if necessary.

Step 2:
Verification.
Option (2) correctly identifies these three pillars that form the lifecycle of project management.