Question:

In a film production budget, the amount spent on the principal creative elements is referred as :

Updated On: Jun 13, 2024
  • Studio Budget
  • Contingent Budget
  • Above the line costs
  • Below the line costs
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct option is (C) : Above the line costs