Step 1: Understand the milling operation and metal removal rate. 
In milling, the metal removal rate (MRR) is the volume of material removed per unit time. It is given by:
\[
\text{MRR} = \text{depth of cut} \times \text{width of cut} \times \text{feed rate},
\]
where:
 Depth of cut (\( d \)): The depth of material removed in one pass,
 Width of cut (\( w \)): The width of the material being removed,
 Feed rate (\( f \)): The speed at which the workpiece moves relative to the cutter (in mm/min).
Step 2: Identify the given values. 
 Metal removal rate: \( \text{MRR} = 30 \, \text{cm}^3/\text{min} = 30 \times 10^3 \, \text{mm}^3/\text{min} \) (since \( 1 \, \text{cm}^3 = 1000 \, \text{mm}^3 \)),
 Depth of cut: \( d = 5 \, \text{mm} \),
 Width of cut: \( w = 100 \, \text{mm} \).
We need to find the feed rate \( f \) in mm/min.
Step 3: Set up the equation for MRR. 
\[
\text{MRR} = d \times w \times f,
\]
\[
30 \times 10^3 = 5 \times 100 \times f,
\]
\[
30,000 = 500 \times f.
\]
Step 4: Solve for the feed rate. 
\[
f = \frac{30,000}{500},
\]
\[
f = 60 \, \text{mm/min}.
\]
Step 5: Evaluate the options. 
 (1) 30 mm/min: Incorrect, as the calculated feed rate is 60 mm/min. Incorrect.
 (2) 60 mm/min: Matches the calculated feed rate. Correct.
 (3) 75 mm/min: Incorrect, as the calculated value is lower. Incorrect.
 (4) 150 mm/min: Incorrect, as the calculated value is much lower. Incorrect.
Step 6: Select the correct answer. 
The rate of feed is 60 mm/min, matching option (2).