1. >GATE ME
  2. >Mechanical Engineering
Found 1  QuestionSET DEFAULT
Selected Filters
    GATE ME Mechanical Engineering Project Management
Exams
Years
Subjects
Topics

List of top Mechanical Engineering Questions on Project Management asked in GATE ME

Activities A, B, C, and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other. 

The probability that the project will be completed within 40 days is _________ (round off to two decimal places).

  • GATE ME - 2021
  • GATE ME
  • Mechanical Engineering
  • Project Management