A construction project consists of 7 activities. These activities, their connecting events, and the three PERT times (optimistic, likely, and pessimistic), in days, are listed in the table below. The project starts on 27th July 2026. Assuming no holidays for the entire duration of the project except 15th August 2026, the expected date of completion of the project will be
August 2026 (mention the date in integer).
| Activity | Connecting Events | Three PERT Times (in Days) |
| P | 1 to 2 | 4 - 6 - 8 |
| Q | 1 to 3 | 5 - 6 - 13 |
| R | 2 to 5 | 6 - 8 - 22 |
| S | 2 to 3 | 8 - 11 - 14 |
| T | 3 to 5 | 2 - 4 - 12 |
| U | 3 to 4 | 4 - 8 - 18 |
| V | 4 to 5 | 5 - 7 - 15 |