Step 1: Understanding the Concept:
This question tests knowledge of the rules for construction and installation of weirs for flow measurement.
Step 2: Detailed Explanation:
The correct rules for weir construction and installation are:
A. Weir should be installed in a straight line at right angle to the direction of flow: Correct.
C. Crest and sides of the edge should be sharp: Correct (for sharp-crested weirs).
D. Velocity of approach of water to the weir should be negligible: Correct.
E. The head over the weir should be measured on the upstream side at a distance of at least 4 times the head of flow: Correct.
B. Velocity of approach should be maximum: Incorrect (it should be negligible).
Thus, A, C, D, and E are correct.
Step 3: Final Answer:
Thus, the correct answer is A, C, D, and E only, which corresponds to option (C).