“Section 55 of the Indian Contract Act says that when a party to a contract promises to do a certain thing within a specified time but fails to do so, the contract or so much of it as has not been performed, becomes voidable at the option of the promisee if the intention of the parties was, that time should be of the essence of the contract. If time is not the essence of the contract, the contract does not become voidable by the failure to do such thing on or before the specified time but the promisee is entitled to compensation from the promisor for any loss occasioned to him by such failure. Further, if in case of a contract voidable on account of the promisor’s failure to perform his promise within the time agreed and the promisee accepts performance of such promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of such acceptance he gives notice to the promisor of his intention to do so.
Sections 73 and 74 deal with consequences of breach of contract. Heading of Sec tion 73 is compensation for loss or damage caused by breach of contract. When a contract is broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract compensation for any loss or damage caused to him thereby which naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach of it. On the other hand, Section 74 deals with compen sation for breach of contract where penalty is stipulated for. When a contract is broken, if a sum is mentioned in the contract as the amount to be paid in case of such breach or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled whether or not actually damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or the penalty stipulated for.”
tracted from: Consolidated Construction Consortium Limited v Software Technol ogy Parks of India 2025 INSC 574
This question asks which factor is NOT correctly used to establish that time is of the essence of a contract under Section 55 of the Indian Contract Act. Since three options describe genuine indicators that time is of the essence, and one describes an indicator that actually points to the opposite conclusion, we assess each option against what courts actually treat as evidence on this issue.
Options (A), (B) and (C) are all genuine, well recognised ways of ascertaining that time is of the essence, while option (D) actually signals the contrary conclusion, so it cannot be used to establish that time is essential.
Therefore, the correct answer is The nature of the contract that provides for an extension of time or liquidated damages for delays.
Section 74 of the Indian Contract Act deals with the measure of compensation payable when a contract fixes a sum as liquidated damages or a penalty for breach. A case is a leading case on Section 74 only if its core holding interprets or applies this specific rule on stipulated damages and penalties. Testing each case listed below against that requirement shows which one does not belong.
Since (A), (B) and (C) each turn on the interpretation of Section 74, while (D) turns on Section 56, the case that is not a leading judgment on Section 74 is Satyabrata Ghose v Mugneeram Bangur and Co.
Therefore, the correct answer is Satyabrata Ghose v Mugneeram Bangur & Co 1954 SCR 310.
This question tests the general common law rule on whether non financial or emotional harm can be compensated as damages for breach of contract. The starting rule is that contract damages aim to put the injured party in the financial position they would have been in had the contract been performed, and that purpose does not usually extend to emotional or reputational harm. Testing each option against that rule identifies the correct proposition.
Only option (A) states the rule as it actually stands, that non pecuniary harms such as hurt feelings, mental distress, loss of reputation and social discredit are not, as a general rule, compensable through contract damages.
Therefore, the correct answer is In general, no damages in contract are awarded for injury to plaintiff's feelings or for mental distress, loss of reputation or social discredit caused by the breach of contract.
Section 74 of the Indian Contract Act provides that when a contract names a sum as the amount payable on breach, whether that sum is called liquidated damages or a penalty, the party complaining of breach can recover only reasonable compensation, not exceeding the sum named, and this holds regardless of whether actual loss is proved to have been caused. Checking each option against this text shows which propositions are correct.
Because (A) and (B) both correctly state the reasonable compensation cap for liquidated damages and penalty sums respectively, while (C) wrongly universalises the exception on proof of loss, the fully correct proposition is the one combining (A) and (B).
Therefore, the correct answer is Both (A) and (B).
This question asks which provision of the Indian Contract Act governs forfeiture of earnest money under a contract. The answer depends on correctly matching what each of Sections 55, 73, 74 and 75 actually covers to the specific situation of a buyer losing a deposit on default.
Since a forfeiture of earnest money clause is a sum stipulated in advance as the consequence of default, and Section 74 is the specific provision governing such stipulated sums, it is the section that applies, subject to the qualification that Section 74 has no application to forfeiture happening under the terms of a public auction before any agreement is reached.
Therefore, the correct answer is Section 74.