Comprehension

“Section 55 of the Indian Contract Act says that when a party to a contract promises to do a certain thing within a specified time but fails to do so, the contract or so much of it as has not been performed, becomes voidable at the option of the promisee if the intention of the parties was, that time should be of the essence of the contract. If time is not the essence of the contract, the contract does not become voidable by the failure to do such thing on or before the specified time but the promisee is entitled to compensation from the promisor for any loss occasioned to him by such failure. Further, if in case of a contract voidable on account of the promisor’s failure to perform his promise within the time agreed and the promisee accepts performance of such promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of such acceptance he gives notice to the promisor of his intention to do so.
Sections 73 and 74 deal with consequences of breach of contract. Heading of Sec tion 73 is compensation for loss or damage caused by breach of contract. When a contract is broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract compensation for any loss or damage caused to him thereby which naturally arose in the usual course of things from such breach or which the parties knew when they made the contract to be likely to result from the breach of it. On the other hand, Section 74 deals with compen sation for breach of contract where penalty is stipulated for. When a contract is broken, if a sum is mentioned in the contract as the amount to be paid in case of such breach or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled whether or not actually damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or the penalty stipulated for.” 
tracted from: Consolidated Construction Consortium Limited v Software Technol ogy Parks of India 2025 INSC 574

Question: 1

Whether time is of essence or not is a question of fact, and the real test is the parties' intention. Which amongst the following is not correct in ascertaining the intention of the parties with respect to "time is of essence".

Show Hint

Remember that a clause for liquidated damages or extension of time usually implies that the parties foresaw a delay and pre-agreed on the consequence, which is compensation, not termination. This is a strong indicator that time is not of the essence.
Updated On: Jul 10, 2026
  • The express words used in the contract.
  • The nature of the property which forms the subject-matter of the contract.
  • The nature of the contract and the surrounding circumstances.
  • The nature of the contract that provides for an extension of time or liquidated damages for delays
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Approach Solution - 1

Step 1: Understanding the Question:
The question asks to identify which of the given options is NOT a correct factor or test for determining whether time is of the essence in a contract. The core issue is how the intention of the parties regarding the timeliness of performance is determined.
Step 2: Detailed Explanation:
According to Section 55 of the Indian Contract Act, whether time is of the essence depends on the intention of the parties. This intention is gathered from several factors.
(A) The express words used in the contract: This is the most direct way to determine the parties' intention. If the contract explicitly states that "time is of the essence," courts will generally uphold this. So, this is a correct factor.
(B) The nature of the property which forms the subject-matter of the contract: If the subject matter is perishable goods or items with fluctuating market values, time is usually considered to be of the essence. So, this is a correct factor.
(C) The nature of the contract and the surrounding circumstances: In commercial or business contracts, time is generally presumed to be of the essence. The context in which the contract was made is crucial. So, this is a correct factor.
(D) The nature of the contract that provides for an extension of time or liquidated damages for delays: This statement is the one that is not entirely correct in the way it is framed as a test. The presence of a clause for extension of time or for payment of liquidated damages for delays is indeed a factor to be considered. However, it is generally considered strong evidence that time is NOT of the essence. The parties have contemplated a possible delay and have provided a remedy for it (compensation), which indicates that they did not intend for the contract to become voidable merely due to delay. Therefore, while it is a factor in "ascertaining the intention," its inclusion as a general test for determining if time is of the essence is misleading. The other three options are direct tests to establish that time is of the essence. The presence of a liquidated damages clause is an indicator pointing to the contrary conclusion. Thus, in the context of identifying a correct test for "time is of essence", this one is the outlier.
Step 3: Final Answer:
Options (A), (B), and (C) are well-established tests for determining if time is of the essence. Option (D) describes a contractual feature that typically indicates that time is not of the essence. Therefore, it is not a correct factor for ascertaining that time is of the essence, making it the correct answer to the question.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

This question asks which factor is NOT correctly used to establish that time is of the essence of a contract under Section 55 of the Indian Contract Act. Since three options describe genuine indicators that time is of the essence, and one describes an indicator that actually points to the opposite conclusion, we assess each option against what courts actually treat as evidence on this issue.

  1. The express words used in the contract: When a contract states directly that time is of the essence, or uses language that fixes a date with a stated consequence for delay, this is the strongest and most direct evidence of the parties' intention. This option is a correct method of ascertaining intention, so it is not the answer.
  2. The nature of the property which forms the subject matter of the contract: Courts look at what is being contracted for. Perishable goods, shares whose price moves daily, or goods needed for a specific event point toward time being essential, while immovable property contracts are usually read the opposite way. Since this is a genuine and recognised test, it is not the answer.
  3. The nature of the contract and the surrounding circumstances: Commercial contracts made in a business setting where delay causes real loss are generally read as making time essential, and the context in which the agreement was struck is a standard factor courts weigh. This is also a correct and recognised test, so it is not the answer.
  4. The nature of the contract that provides for an extension of time or liquidated damages for delays: A contract that itself provides a mechanism to extend the deadline, or that fixes a sum payable as damages if delay occurs, shows that the parties expected delay might happen and built in a remedy for it rather than treating any delay as fatal to the contract. Courts treat such a clause as evidence that time is NOT of the essence, not evidence that it is. Framing this as a test for showing time IS essential gets the direction backward.

Options (A), (B) and (C) are all genuine, well recognised ways of ascertaining that time is of the essence, while option (D) actually signals the contrary conclusion, so it cannot be used to establish that time is essential.

Therefore, the correct answer is The nature of the contract that provides for an extension of time or liquidated damages for delays.

Was this answer helpful?
0
0
Question: 2

Which of the following is NOT a leading judgement on section 74 of the Indian Contract Act:

Show Hint

For law entrance exams, it's crucial to associate landmark cases with the specific legal doctrines or sections they interpret. For example: Satyabrata Ghose → Frustration (Sec 56), Fateh Chand → Penalty (Sec 74), Carlill v Carbolic Smoke Ball → General Offer.
Updated On: Jul 10, 2026
  • Kailash Nath Associates v Delhi Development Authority [2015] 1 SCR 627.
  • ONGC Ltd v Saw Pipes Ltd (2003) 5 SCC 705.
  • Fateh Chand v Balkishan Dass (1964) 1 SCR 515.
  • Satyabrata Ghose v Mugneeram Bangur\ & Co 1954 SCR 310.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Approach Solution - 1

Step 1: Understanding the Question:
The question requires identifying the court case from the given options that is not a landmark or leading judgment concerning Section 74 of the Indian Contract Act, 1872. Section 74 deals with compensation for breach of contract where a penalty or liquidated damages are stipulated.
Step 2: Detailed Explanation:
Let's analyze each option:
(A) Kailash Nath Associates v Delhi Development Authority (2015): This is a modern landmark Supreme Court judgment that extensively clarified the principles of Section 74. It held that damages awarded under Section 74 must be reasonable and a genuine pre-estimate of the loss, and proof of loss is necessary unless it is difficult or impossible to prove. It is a leading case on Section 74.
(B) ONGC Ltd v Saw Pipes Ltd (2003): This is another significant Supreme Court case that interpreted Section 74. It dealt with the concept of "public policy" and laid down that the stipulated sum could be awarded as compensation if it is a genuine pre-estimate of loss, especially in cases where proving the actual loss is difficult. It is a leading case on Section 74.
(C) Fateh Chand v Balkishan Dass (1964): This is a foundational Supreme Court case on Section 74. The court held that Section 74 applies to all stipulations by way of penalty, including forfeiture of earnest money, and the court will only grant reasonable compensation not exceeding the stipulated amount. It is a cornerstone judgment for Section 74.
(D) Satyabrata Ghose v Mugneeram Bangur \ & Co (1954): This is a landmark Supreme Court judgment, but it is the leading authority on the doctrine of frustration of contract, which is covered under Section 56 of the Indian Contract Act. It does not primarily deal with Section 74.
Step 3: Final Answer:
Based on the analysis, Satyabrata Ghose v Mugneeram Bangur \ & Co is a leading case on Section 56 (frustration of contract), not Section 74 (liquidated damages and penalties). Therefore, it is the correct answer.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

Section 74 of the Indian Contract Act deals with the measure of compensation payable when a contract fixes a sum as liquidated damages or a penalty for breach. A case is a leading case on Section 74 only if its core holding interprets or applies this specific rule on stipulated damages and penalties. Testing each case listed below against that requirement shows which one does not belong.

  1. Kailash Nath Associates v Delhi Development Authority: This 2015 Supreme Court decision is directly about Section 74. It held that a party claiming the stipulated sum must still show it suffered a loss unless proving the loss is genuinely difficult, and that the sum named in the contract only fixes the outer limit of what can be awarded. Its holding is squarely about Section 74, so it counts as a leading case.
  2. ONGC Ltd v Saw Pipes Ltd: Although this case is more widely known for its discussion of public policy in the context of setting aside arbitral awards, the underlying dispute concerned whether the sum stipulated in the contract as damages for delay could be awarded without independent proof of loss, which the Court answered by applying Section 74. Because the Section 74 question was central to the decision, it is treated as a leading authority on the section.
  3. Fateh Chand v Balkishan Dass: This is the foundational Supreme Court ruling that first explained how Section 74 applies uniformly to any stipulation by way of penalty, including forfeiture of earnest money, and that a court may award reasonable compensation up to the stated sum. This is one of the earliest and most cited authorities specifically on Section 74.
  4. Satyabrata Ghose v Mugneeram Bangur and Co: This case concerns whether a contract for the sale of land stood frustrated because of requisition of the land during the Second World War, which is a question governed by Section 56, not Section 74. Its holding has nothing to do with stipulated damages or penalty clauses, so it does not belong on a list of Section 74 authorities.

Since (A), (B) and (C) each turn on the interpretation of Section 74, while (D) turns on Section 56, the case that is not a leading judgment on Section 74 is Satyabrata Ghose v Mugneeram Bangur and Co.

Therefore, the correct answer is Satyabrata Ghose v Mugneeram Bangur & Co 1954 SCR 310.

Was this answer helpful?
0
0
Question: 3

Which of the following is a CORRECT proposition as regards award of damages in contract:

Show Hint

Remember the core purpose of contract damages: to compensate for financial loss, not to punish the breacher or soothe hurt feelings. Damages for emotional distress are the exception, not the rule.
Updated On: Jul 10, 2026
  • In general, no damages in contract are awarded for injury to plaintiff's feelings or for mental distress, loss of reputation or social discredit caused by the breach of contract.
  • In general, damages in contract are awarded for anguish and vexation caused by the breach of contract.
  • In general, damages in contract are awarded for anguish and loss of reputation, but not for social discredit caused by the breach of contract.
  • In general, damages in contract are awarded for emotional distress, but not for mental agony caused by the breach of contract.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Approach Solution - 1

Step 1: Understanding the Question:
The question asks to identify the correct general principle governing the award of damages for non-pecuniary (non-financial) losses in the law of contract.
Step 2: Detailed Explanation:
The fundamental principle of damages in contract law, established in the case of Hadley v. Baxendale, is to compensate the injured party for their financial losses that arise naturally from the breach. The goal is to put the plaintiff in the same financial position they would have been in had the contract been performed.
This principle generally excludes compensation for non-pecuniary losses.
- Injury to feelings, mental distress, anguish, vexation: The law generally does not award damages for these emotional harms in commercial contract breaches. There are very limited exceptions, for instance, in contracts where the primary purpose was to provide enjoyment or peace of mind (like a holiday package), but the general rule is one of no recovery.
- Loss of reputation or social discredit: Damages for loss of reputation are typically pursued in the law of torts (defamation), not contract. A breach of contract, even if it harms a person's reputation, is not generally a ground for awarding such damages.
Let's evaluate the options based on this principle:
(A) This option correctly states the general rule: no damages are awarded for injury to feelings, mental distress, loss of reputation, or social discredit. This is the correct proposition.
(B) This option claims damages are awarded for anguish and vexation, which contradicts the general rule.
(C) This option incorrectly suggests that damages for anguish and loss of reputation are awarded, which is contrary to the general principle.
(D) This option creates an artificial and incorrect distinction between "emotional distress" and "mental agony" and wrongly suggests damages are available for the former.
Step 3: Final Answer:
Option (A) accurately represents the general common law position on damages for non-pecuniary losses in contract law.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

This question tests the general common law rule on whether non financial or emotional harm can be compensated as damages for breach of contract. The starting rule is that contract damages aim to put the injured party in the financial position they would have been in had the contract been performed, and that purpose does not usually extend to emotional or reputational harm. Testing each option against that rule identifies the correct proposition.

  1. No damages for injury to feelings, mental distress, loss of reputation or social discredit: This matches the general rule exactly. Contract damages are compensatory for the bargain lost, not for emotional suffering, and courts have consistently refused to extend contract damages to hurt feelings, humiliation, or damage to standing in society, treating those as matters for the law of tort such as defamation rather than contract. This is the correct proposition.
  2. Damages awarded for anguish and vexation: This directly contradicts the general rule. Anguish and vexation are emotional states, and awarding damages for them as a matter of course would blur the line between contract and tort claims for mental suffering, which the law does not generally allow outside a narrow set of exceptions such as contracts made specifically for enjoyment or peace of mind.
  3. Damages awarded for anguish and loss of reputation, but not social discredit: This creates an artificial split between loss of reputation and social discredit that the law does not draw. Both are treated the same way, as non pecuniary harms that fall outside ordinary contract damages, so singling one out as compensable while excluding the other misstates the rule.
  4. Damages awarded for emotional distress, but not mental agony: This too invents a distinction between emotional distress and mental agony that has no basis in the general rule. Both are forms of non pecuniary harm and both are, as a general rule, excluded from contract damages in the same way.

Only option (A) states the rule as it actually stands, that non pecuniary harms such as hurt feelings, mental distress, loss of reputation and social discredit are not, as a general rule, compensable through contract damages.

Therefore, the correct answer is In general, no damages in contract are awarded for injury to plaintiff's feelings or for mental distress, loss of reputation or social discredit caused by the breach of contract.

Was this answer helpful?
0
0
Question: 4

Which of the following is/are CORRECT proposition(s) as regards the law on damages for the breach of contract under section 74 of the Indian Contract Act:

Show Hint

Under Section 74, the key takeaways are: 1) Indian law treats liquidated damages and penalties similarly. 2) The court awards 'reasonable compensation'. 3) The stipulated amount is the maximum limit (cap), not the automatic award. 4) Proof of loss is required unless it's impossible or very difficult to prove.
Updated On: Jul 10, 2026
  • Where a sum is named in the contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated.
  • In cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded, not exceeding the penalty so stated.
  • The expression 'whether or not actual damage or loss is proved to have been caused thereby' in section 74 means that in every case the proof of actual damage or loss has been dispensed with.
  • Both (A) and (B).
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Approach Solution - 1

Step 1: Understanding the Question:
The question asks to identify the correct legal proposition(s) concerning Section 74 of the Indian Contract Act, which deals with stipulated damages and penalties.
Step 2: Detailed Explanation:
The text provided in the passage itself summarizes Section 74. Let's analyze each proposition:
(A) "Where a sum is named in the contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated." This is the essence of Section 74. Unlike English law, Indian law does not distinguish between liquidated damages (a genuine pre-estimate of loss) and a penalty (a deterrent). In both cases, the court has the discretion to award what it considers 'reasonable compensation', with the stipulated sum acting as an upper limit. This statement is correct.
(B) "In cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded, not exceeding the penalty so stated." This is also correct for the same reason as above. Section 74 explicitly covers sums named as penalties, and the treatment is the same: award of reasonable compensation up to the stipulated amount.
(C) "The expression 'whether or not actual damage or loss is proved to have been caused thereby' in section 74 means that in every case the proof of actual damage or loss has been dispensed with." This is an incorrect interpretation of the law. The Supreme Court in Kailash Nath Associates v. DDA (2015) clarified this phrase. It held that the expression only applies in situations where it is difficult or impossible to prove the actual loss. If the loss is ascertainable, the plaintiff must prove it. Therefore, proof of loss is not dispensed with in every case. This statement is incorrect.
(D) Since propositions (A) and (B) are both correct statements of the law under Section 74, this option is the most accurate and complete answer.
Step 3: Final Answer:
Both (A) and (B) are correct propositions of law under Section 74 of the Indian Contract Act. Therefore, option (D) is the correct choice.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

Section 74 of the Indian Contract Act provides that when a contract names a sum as the amount payable on breach, whether that sum is called liquidated damages or a penalty, the party complaining of breach can recover only reasonable compensation, not exceeding the sum named, and this holds regardless of whether actual loss is proved to have been caused. Checking each option against this text shows which propositions are correct.

  1. Reasonable compensation not exceeding the amount named as liquidated damages: This restates the operative rule of Section 74 for the case where the sum is called liquidated damages. Indian law, unlike English law, does not give special treatment to sums genuinely pre estimated as loss. Even a liquidated damages clause only caps recovery at reasonable compensation, so this proposition is correct.
  2. Reasonable compensation not exceeding the amount named as penalty: Section 74 explicitly covers sums stipulated by way of penalty in the same breath as liquidated damages, and applies the identical cap of reasonable compensation. This proposition is also correct.
  3. The phrase on proof of actual damage means proof is dispensed with in every case: This misreads the text. Courts have clarified that the phrase only relieves a claimant of proving loss where proving the loss is difficult or impossible by its nature. Where the loss is capable of being proved, the claimant must still prove it, and the reasonable compensation awarded is measured against that proof. So proof is not dispensed with in every case, and this proposition is incorrect.
  4. Both (A) and (B): Since both (A) and (B) independently state the correct legal position while (C) does not, this combined option correctly captures the full and accurate statement of the law.

Because (A) and (B) both correctly state the reasonable compensation cap for liquidated damages and penalty sums respectively, while (C) wrongly universalises the exception on proof of loss, the fully correct proposition is the one combining (A) and (B).

Therefore, the correct answer is Both (A) and (B).

Was this answer helpful?
0
0
Question: 5

__________ will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, section 74 would have no application:

Show Hint

Always remember that forfeiture of earnest money is not automatic. It is subject to the test of reasonableness under Section 74. The amount forfeited must be a genuine pre-estimate of the loss suffered by the non-defaulting party.
Updated On: Jul 10, 2026
  • Section 55.
  • Section 73.
  • Section 74.
  • Section 75.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Approach Solution - 1

Step 1: Understanding the Question:
The question asks to identify the section of the Indian Contract Act that governs the forfeiture of earnest money under a contract.
Step 2: Detailed Explanation:
Earnest money is a deposit made by a buyer as a manifestation of good faith to bind a contract. If the buyer defaults, this amount is often forfeited. The question is how the law treats such forfeiture clauses.
The Supreme Court in the landmark case of Fateh Chand v. Balkishan Dass (1964) held that the principles of Section 74 apply to the forfeiture of earnest money. The court reasoned that a clause for forfeiture is a "stipulation by way of penalty."
Therefore, even if there is a clause for forfeiture of earnest money, the court will not allow the entire amount to be forfeited if it is penal in nature. The party forfeiting the money is only entitled to "reasonable compensation" for the loss suffered, and the amount of earnest money serves as the upper limit.
Let's review the options:
- (A) Section 55 deals with the time of performance, which is not directly relevant.
- (B) Section 73 provides for general damages where no amount is stipulated. Since earnest money involves a stipulated amount for forfeiture, the more specific Section 74 applies.
- (C) Section 74 deals with contracts containing a stipulation by way of penalty, which has been interpreted by courts to include clauses for the forfeiture of earnest money. This is the correct section.
- (D) Section 75 deals with compensation for a party who rightfully rescinds a contract, which is a related but different context. Section 74 is the specific provision for quantifying damages where a penalty (like forfeiture) is stipulated.
Step 3: Final Answer:
Section 74 of the Indian Contract Act applies to cases of forfeiture of earnest money under a contract.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

This question asks which provision of the Indian Contract Act governs forfeiture of earnest money under a contract. The answer depends on correctly matching what each of Sections 55, 73, 74 and 75 actually covers to the specific situation of a buyer losing a deposit on default.

  1. Section 55: This section deals with the consequences of failing to perform a promise within a specified time, and whether that makes the contract voidable, depending on whether time was of the essence. It has nothing to do with sums forfeited on default and does not govern earnest money.
  2. Section 73: This section provides for ordinary compensation for loss caused by breach, calculated based on what naturally arose from the breach or was in the contemplation of the parties, in situations where the contract has NOT itself fixed any sum for breach. Since a forfeiture clause is a stipulated sum agreed in advance, Section 73 is the wrong fit, and the more specific provision covering pre fixed sums takes over instead.
  3. Section 74: This section governs situations where the contract itself names a sum, whether as liquidated damages or as a penalty, payable on breach. Forfeiture of earnest money is exactly this kind of pre fixed sum, agreed at the time of contracting as the consequence of the buyer's default, so courts have consistently applied Section 74 to cap what can actually be kept at reasonable compensation. This is the correct fit.
  4. Section 75: This section entitles a party who rightfully rescinds a contract to compensation for damage suffered through non fulfilment. It governs the position of a party terminating the contract, not the separate question of how a pre fixed forfeiture sum is treated, so it does not apply here.

Since a forfeiture of earnest money clause is a sum stipulated in advance as the consequence of default, and Section 74 is the specific provision governing such stipulated sums, it is the section that applies, subject to the qualification that Section 74 has no application to forfeiture happening under the terms of a public auction before any agreement is reached.

Therefore, the correct answer is Section 74.

Was this answer helpful?
0
0

Top CLAT PG Questions

View More Questions