Step 1: Work done by P in 9 days.
\[
\text{Work completed by P in 9 days} = \frac{13}{20} \quad \Rightarrow \quad \text{Work completed by P in 1 day} = \frac{13}{20} \div 9 = \frac{13}{180}.
\]
Step 2: Remaining work after P's 9 days of work.
\[
\text{Remaining work} = 1 - \frac{13}{20} = \frac{7}{20}.
\]
Step 3: Work done by P and Q together in 4 days.
\[
\text{Work completed by P and Q together in 4 days} = \frac{7}{20} \quad \Rightarrow \quad \text{Work done by P and Q together in 1 day} = \frac{7}{20} \div 4 = \frac{7}{80}.
\]
Step 4: Time taken for P and Q to complete the entire work.
Since the combined rate of P and Q is \( \frac{7}{80} \) work per day, the time taken to complete the entire work is:
\[
\text{Total time} = \frac{1}{\frac{7}{80}} = \frac{80}{7} = 11 \frac{3}{7} \text{ days}.
\]