Step 1: Understanding the Concept:
Subsurface tile drain installation must follow a strict downstream-to-upstream sequence to maintain continuous gravitational trench dewatering during excavation.
Step 2: Detailed Explanation:
Standard civil and drainage engineering installation practice:
Construction and pipe laying of a subsurface drainage network must always start at the Outlet and proceed progressively upstream (Outlet $\rightarrow$ Main Collector Drain $\rightarrow$ Sub-mains $\rightarrow$ Laterals).
This ensures that:
1. Any groundwater seepage entering the trench during excavation drains out immediately by gravity.
2. Pipe grade and invert elevations are accurately established relative to the permanent outlet datum.
Step 3: Final Answer:
Therefore, construction should begin from the Outlet, matching option (A).