Step 1: Understanding the Concept:
Time and work problems are solved using the concept of work rates.
The work rate of an individual is the fraction of the total job they can complete in a single unit of time (such as one day).
When individuals work together, their individual work rates are added to find their combined work rate:
\[ \text{Rate}_{\text{together}} = \text{Rate}_A + \text{Rate}_B \]
Key Formula or Approach:
Let the time taken by Anil alone to complete the job be $A$ days, and the time taken by Bijal alone be $B$ days.
If they can complete the job together in $T$ days, their relationship is expressed as:
\[ \frac{1}{A} + \frac{1}{B} = \frac{1}{T} \]
Step 2: Detailed Explanation:
Let us identify the given values and solve for $B$:
- Combined time taken ($T$) $= 4\text{ days}$
- Combined work rate $= \frac{1}{4}$ of the job per day.
- Time taken by Anil alone ($A$) $= 12\text{ days}$
- Anil's work rate $= \frac{1}{12}$ of the job per day.
Substitute these rates into the work rate equation:
\[ \frac{1}{12} + \frac{1}{B} = \frac{1}{4} \]
Isolate the term $\frac{1}{B}$:
\[ \frac{1}{B} = \frac{1}{4} - \frac{1}{12} \]
Find a common denominator for the fractions on the right side (which is $12$):
\[ \frac{1}{B} = \frac{3}{12} - \frac{1}{12} \]
\[ \frac{1}{B} = \frac{2}{12} \]
Simplify the fraction:
\[ \frac{1}{B} = \frac{1}{6} \]
Solve for $B$:
\[ B = 6 \]
Therefore, Bijal working alone will take $6\text{ days}$ to complete the entire job.
Step 3: Final Answer:
Bijal alone will take 6 days to complete the job.
Therefore, the correct option is (A).