Question:

Ajay can complete a work in 9 days working for 8 hours a day. Vijay can complete the same work in 16 days working for 4 hours a day. If they work together to complete the work , then what is the approximate percentage of work done by Vijay?

Updated On: Oct 25, 2024
  • 51%
  • 53%
  • 55%
  • 58%
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct answer is (B);53%