Question:

A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time? [This Question was asked as TITA] 

Updated On: Sep 17, 2024
  • 10
  • 40
  • 50
  • 60
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Approach Solution - 1

 MenTunnelDays
Initial1401.5 km60
RemainingX4.5 km140

\(X = 140×\frac{4.5}{1.5}×\frac{60}{140} = 180\)

Additional men required = \(180-140 = 40\)

Was this answer helpful?
0
0
Hide Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

A contractor agreed to build a road in \(200\) days and had \(140\) persons to do  work.
After \(60\) days, only \(\frac 14^{th}\) of the road could be build.
We know that,
\(\frac {M_1 × D_1 × T_1}{W_1}= \frac {M_2 × D_2 × T_2}{W_2}\)
Amount of work remaining \(= 1-\frac 14 = \frac 34\) unit of work.
Number of days in which the remaining work needs to be completed \(= 200 - 140 = 60\) days.
Let \(x \) persons be extra needed to finish the work.

\(\frac {140 × 60}{\frac 14}= \frac {(140 + x) × 140}{\frac 34}\)

\(4 × 60= \frac {(140 + x) × 4}{3}\)
\(140+x=180\)
\(x=180-140\)
\(x=40\)

So, the answer is \(40\).

Was this answer helpful?
1
0