It can be observed that these penalties are in an A.P. having first term as 200 and common difference as 50.
\(a = 200\) and \(d = 50\)
Penalty that has to be paid if he has delayed the work by 30 days
= \(S_{30}\)
= \(\frac {30}{2} [2\times 200 + (30-1)50]\)
= \(15 [400 + 1450]\)
= \(15 (185\)0)
= \(27750\)
Therefore, the contractor has to pay Rs. 27750 as penalty.