Question:

A certain number of persons were hired to complete a job in 60 days. If 8 more persons are hired then the job could be completed in 10 days less. How many persons were hired originally?

Show Hint

For a fixed amount of work, if the number of workers increases, the time decreases proportionally. Use the relation: \[ M_1D_1=M_2D_2. \]
Updated On: Jun 12, 2026
  • \(50\)
  • \(48\)
  • \(45\)
  • \(40\)
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Concept: For the same amount of work, \[ \text{Men} \times \text{Days} = \text{Constant} \] This is the principle of inverse proportion.

Step 1:
Assume the original number of persons is \(x\). Initially, \[ x \text{ persons} \] complete the work in \[ 60 \text{ days} \] Hence total work: \[ 60x \] man-days.

Step 2:
Form the second condition. After hiring 8 additional persons, \[ x+8 \] persons complete the work in \[ 60-10=50 \] days. Thus, \[ 50(x+8) \] man-days. Since total work remains unchanged, \[ 60x=50(x+8) \]

Step 3:
Solve the equation. \[ 60x=50x+400 \] \[ 10x=400 \] \[ x=40 \] Therefore, the number of persons originally hired was \[ \boxed{40} \]
Was this answer helpful?
0
0