List of top Industrial Engineering Questions on Assembly line balancing asked in GATE PI

A machine component is processed at 5 workstations sequentially. The cycle time (in seconds) for each workstation is given. In mass production, the number of components produced per hour (steady state) is \(\underline{\hspace{2cm}}\). [in integer] \[ \begin{array}{|c|c|} \hline \text{Workstation} & \text{Cycle time (sec)} \\ \hline \text{WS-1} & 85 \\ \text{WS-2} & 55 \\ \text{WS-3} & 90 \\ \text{WS-4} & 65 \\ \text{WS-5} & 70 \\ \hline \end{array} \]
  • GATE PI - 2022
  • GATE PI
  • Industrial Engineering
  • Assembly line balancing