List of top Materials, Manufacturing & Industrial Engineering Questions on Aggregate production planning asked in GATE ME
Parts P1--P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is ____________________ hours.
GATE ME - 2022
GATE ME
Materials, Manufacturing & Industrial Engineering
Aggregate production planning