An activated sludge process (ASP) is designed for secondary treatment of 7500 m\(^3\)/day of municipal wastewater. After primary clarifier, the ultimate BOD of the influent, which enters into the ASP reactor, is 200 mg/L. Treated effluent after secondary clarifier is required to have an ultimate BOD of 20 mg/L. Mix liquor volatile suspended solids (MLVSS) concentration in the reactor and the underflow is maintained as 3000 mg/L and 12000 mg/L, respectively. The hydraulic retention time and mean cell residence time are 0.2 day and 10 days, respectively. A representative flow diagram of the ASP is shown below. 

The underflow volume (in m}^3\text{/day, round off to one decimal place) of sludge wastage is \(\underline{\hspace{1cm}}\).

  • GATE CE - 2021
  • GATE CE
  • Environmental Engineering
  • Design of Sewer